Updated: Jun 02, 2026
No. of Questions: 67 Questions & Answers with Testing Engine
Download Limit: Unlimited
Our Actual4Cert CIMAPRO15-P01-X1-ENG actual exam cert can provide you with the comprehnsive study points about the acutal test, with which you can have a clear direction during the perparation.The validity and reliability of the CIMAPRO15-P01-X1-ENG actual torrent has helped lots of people get good redsult.Choose our CIMAPRO15-P01-X1-ENG training cert, you will get 100% pass.
Actual4Cert has an unprecedented 99.6% first time pass rate among our customers.
We're so confident of our products that we provide no hassle product exchange.
1. A marketing manager is trying to decide which of four potential selling prices to charge for a new product. The state of the economy is uncertain and may show signs of recession, growth or boom. The manager has prepared a regret matrix showing the regret for each of the possible outcomes depending on the decision made.
If the manager applies the minimax regret criterion to make decisions, which selling price would be chosen?
A) $45
B) $55
C) $40
D) $50
2. CDF is a manufacturing company within the DF group. CDF has been asked to provide a quotation for a contract for a new customer and is aware that this could lead to further orders. As a consequence, CDF will produce the quotation by using relevant costing instead of its usual method of full cost plus pricing. The
following information has been obtained in relation to the contract: Material D 40 tons of material D would be required. This material is in regular use by CDF and has a current purchase price of $38 per ton. Currently, there are 5 tons in inventory which cost $35 per ton. The resale value of the material in inventory is $24 per ton.
Components 4,000 components would be required. These could be bought externally for $15 each or alternatively they could be supplied by RDF, another company within the DF manufacturing group. The variable cost of the component if it were manufactured by RDF would be $8 per unit, and RDF adds 30% to its variable cost to contribute to its fixed costs plus a further 20% to this total cost in order to set its internal transfer price. RDF has sufficient capacity to produce 2,500 components without affecting its ability to satisfy its own external customers. However, in order to make the extra 1,500 components required by CDF, RDF would have to forgo other external sales of $50,000 which have a contribution to sales ratio of 40%.
Labour hours 850 direct labour hours would be required. All direct labour within CDF is paid on an hourly basis with no guaranteed wage agreement. The grade of labour required is currently paid $10 per hour, but department W is already working at 100% capacity. Possible ways of overcoming this problem are:
* Use workers in department Z, because it has sufficient capacity. These workers are paid $15 per hour.
* Arrange for sub-contract workers to undertake some of the other work that is performed in department W.
The sub-contract workers would cost $13 per hour.
Specialist machine The contract would require a specialist machine. The machine could be hired for $15,000 or it could be bought for $50,000. At the end of the contract if the machine were bought, it could be sold for
$30,000. Alternatively, it could be modified at a cost of $5,000 and then used on other contracts instead of buying another essential machine that would cost $45,000. The operating costs of the machine are payable by CDF whether it hires or buys the machine. These costs would total $12,000 in respect of the new contract.
Supervisor The contract would be supervised by an existing manager who is paid an annual salary of $50,000 and has sufficient capacity to carry out this supervision. The manager would receive a bonus of $500 for the additional work.
Development time 15 hours of development time at a cost of $3,000 have already been worked in determining the resource requirements of the contract.
Fixed overhead absorption rate CDF uses an absorption rate of $20 per direct labour hour to recover its general fixed overhead costs. This includes $5 per hour for depreciation.
Calculate the relevant cost of the contract to CDF. You must present your answer in a schedule that clearly shows the relevant cost value for each of the items identified above. You should also explain each relevant cost value you have included in your schedule and why any values you have excluded are not relevant.
Ignore taxation and the time value of money.
Select all the true statements.
A) The total relevant cost was $84 990
B) Development Cost is a relevant cost.
C) General fixed overhead costs are relevant costs.
D) The total relevant cost was $94 740
E) Machine operating costs is a relevant cost.
F) The total relevant cost was $104 320
G) Direct labour cist is a relevant cost
3. A company sells and services photocopying machines. Its sales department sells the machines and consumables, including ink and paper, and its service department provides an after sales service to its customers. The after sales service includes planned maintenance of the machine and repairs in the event of a machine breakdown. Service department customers are charged an amount per copy that differs depending on the size of the machine.
The company's existing costing system uses a single overhead rate, based on total sales revenue from copy charges, to charge the cost of the Service Department's support activities to each size of machine. The Service Manager has suggested that the copy charge should more accurately reflect the costs involved. The company's accountant has decided to implement an activity-based costing system and has obtained the following information about the support activities of the service department:
Calculate the annual profit per machine for each of the three sizes of machine using activity-based costing.
A) Profit Per Machine using ABC: Small $376, Medium $2341, Large $986
B) Profit Per Machine using ABC: Small $186, Medium $1441, Large $2046
C) Profit Per Machine using ABC: Small $196, Medium $1191, Large $1046
D) Profit Per Machine using ABC: Small $166, Medium $1241, Large $746
E) Profit Per Machine using ABC: Small $176, Medium $1341, Large $946
F) Profit Per Machine using ABC: Small $1076, Medium $1041, Large $1946
4. JRL manufactures two products from different combinations of the same resources. Unit selling prices and unit cost details for each product are as follows:
Identify, using graphical linear programming, the weekly production schedule for products J and L that will maximize the profits of JRL during the next four weeks.
A) Optimum plan (including major customer order) is therefore:
W 950 units
R 750 units
X 2,300 units
B) Optimum plan (including major customer order) is therefore:
W 1, 000 units
R 600 units
X 2,000 units
C) Optimum plan (including major customer order) is therefore:
W 910 units
R 800 units
X 2,200 units
D) Optimum plan (including major customer order) is therefore:
W 900 units
R 650 units
X 2,000 units
E) Optimum plan (including major customer order) is therefore:
W 900 units
R 700 units
X 2,100 units
5. RT produces two products from different quantities of the same resources using a just-in-time (JIT) production system. The selling price and resource requirements of each of the products are shown below:
Market research shows that the maximum demand for products R and T during June 2010 is 500 units and
800 units respectively. This does not include an order that RT has agreed with a commercial customer for the supply of 250 units of R and 350 units of T at selling prices of $100 and $135 per unit respectively. Although the customer will accept part of the order, failure by RT to deliver the order in full by the end of June will cause RT to incur a $10,000 financial penalty. At a recent meeting of the purchasing and production managers to discuss the production plans of RT for June, the following resource restrictions for June were identified:
Direct labour hours 7,500 hours
Material A 8,500 kgs
Material B 3,000 litres
Machine hours 7,500 hours
(Refer to previous 2 questions.)
You have now presented your optimum production plan to the purchasing and production managers of RT.
During your presentation it became clear that the predicted resource restrictions were rather optimistic. In fact, the managers agreed that the availability of all of the resources could be as much as 10% lower than their original predictions.
Assuming that RT completes the order with the commercial customer, and using linear programming, show the optimum production plan for RT for June 2010 on the basis that the availability of all resources is 10% lower than originally predicted.
A) The optimal plan is to produce 550 units of Product R and 650 units of product T in addition to the contract.
B) The optimal plan is to produce 510 units of Product R and 720 units of product T in addition to the contract.
C) The optimal plan is to produce 560 units of Product R and 670 units of product T in addition to the contract.
D) The optimal plan is to produce 520 units of Product R and 620 units of product T in addition to the contract.
E) The optimal plan is to produce 500 units of Product R and 550 units of product T in addition to the contract.
F) The optimal plan is to produce 450 units of Product R and 690 units of product T in addition to the contract.
Solutions:
| Question # 1 Answer: A | Question # 2 Answer: A,E,G | Question # 3 Answer: D | Question # 4 Answer: D | Question # 5 Answer: E |
1343 Customer ReviewsCustomers Feedback (* Some similar or old comments have been hidden.)The soft version is very good for me and it helps me face the mistakes I make. very good to pass CIMAPRO15-P01-X1-ENG exam! Cheers!
Great that I can get you! Thank you for the great CIMAPRO15-P01-X1-ENG study materials.
I passed my CIMAPRO15-P01-X1-ENG exams. It is the best braindump I have used. So I will recommend it to all my colleagues. Surely they will pass their exam eaily with the help of Actual4Cert's study materials. Thanks!!!
Thank you guys for the great CIMAPRO15-P01-X1-ENG study material.
Exam dump is still valid.I pass the dump today with only 6 days of studying with the dump file.
The CIMAPRO15-P01-X1-ENG training dumps are well-written and latest for sure. I just took the CIMAPRO15-P01-X1-ENG exam and passed without difficulty. I will buy the other exam braindumps this time.
Valid for sure! Most updated CIMAPRO15-P01-X1-ENG exam questions for me to pass the CIMAPRO15-P01-X1-ENG exam. Don't hesitate, you will pass easily as long as you use it.
So I passed my CIMAPRO15-P01-X1-ENG exam very easily.
Thank you so much Actual4Cert guys.
Actual4Cert's guide is worth every penny!
A unique experience!
Since the fail rate of this CIMAPRO15-P01-X1-ENG exam is high and the exam cost is high, I want to success 100% in one go so I choose Actual4Cert. I am glad about my score. Thank you very much! Without your help, i won't achieve it! Thanks again!
Amazing dumps by Actual4Cert. Question answers were a part of the actual CIMAPRO15-P01-X1-ENG exam. I got 97% marks with the help of these pdf files.
Hi,I just downloaded this CIMAPRO15-P01-X1-ENG dump yesterday and my exam was today. I passed with 80%! Thank you!
My dream to be a certified man came true with great CIMA Certification help from Actual4Cert.
I was not sure that I can make CIMAPRO15-P01-X1-ENG exam in my first go, but with the help of CIMAPRO15-P01-X1-ENG Actual4Cert questions, it just a piece of cake. Thanks you very much!
This time not only i passed, but also i also passed with high scores in my examination. Good guides!
This is the best way to prepare for CIMAPRO15-P01-X1-ENG. I passed my CIMAPRO15-P01-X1-ENG exam. Thanks!
Actual4Cert gave the 100% pass guarantee, then there was the money back guarantee and then there were these very high quality dumps. It's really helpful.
I wrote CIMAPRO15-P01-X1-ENG exam today and remembered every question of CIMAPRO15-P01-X1-ENG dump. I found 90% questions of real exam was what I wrote. Very valid dump!
Can't thank team Actual4Cert enough to help me clear my CIMAPRO15-P01-X1-ENG certification exam. Exam testing software is the best tool to prepare with. I achieved 95% marks.
Dumps did not have all questions. Mostly around 90% but should be good enough to pass with this CIMAPRO15-P01-X1-ENG dump. You should have knowledge too.
Great customers support! when i had an issue with downloading CIMAPRO15-P01-X1-ENG study braindump, i sent an email and they solved the problem immediately. And i passed the exam smoothly today. You can trust this site Actual4Cert.
Actual4Cert CIMAPRO15-P01-X1-ENG study material is valid and latest, which is edited and compiled by our proffessional experts. The high quality and high pass rate is the 100% guarantee of your success in the CIMAPRO15-P01-X1-ENG actual test. You can easily pass with our CIMAPRO15-P01-X1-ENG training torrent at first attempt.
To ensure the best interests of our customer, we have money back guarantee when in case of failure. You just need to send us your failure score scanned, then after confirming, we will give you refund.
You will receieve an email attached with the CIMAPRO15-P01-X1-ENG study questions within 5-10 minutes after purcahse. Download the CIMAPRO15-P01-X1-ENGpractice material and go for study with no time waste. If you do not get the exam material, kindly please contact us at once
All our products are the latest version. If you want to know details about each exam materials, our service will be waiting for you 7*24*365 online. Our exam products will updates with the change of the real CIMAPRO15-P01-X1-ENG test.
All our products can share 365 days free download for updating version from the date of purchase. So don't worry.One year free update is available for all of you.
If there is any update about the CIMAPRO15-P01-X1-ENG study material,our system will automatically send the updated practice material to your payment email.
No. After purchase, our system will set up an account and password by your purchasing information. You can use it directly or you can change your password as you like. No need to register an account yourself.
Yes, we have money back guarantee if you fail exam with our products. Applying for refund is simple that you send email to us for applying refund attached your failure score scanned. Money will be back to your payment email within 7 days.
Online Test Engine can supports Windows / Mac / Android / iOS, etc., because it is the software based on WEB browser. You can use it on any electronic device and practice with self-paced. Online Test Engine supports offline practice, while the precondition is that you should run it with the internet at the first time. Self Test Engine is suitable for windows operating system, running on the Java environment, and can install on multiple computers. PDF Version: can be read under the Adobe reader, or many other free readers, including OpenOffice, Foxit Reader and Google Docs.
Self Test Software can be downloaded in more than two hundreds computers. It is no limitation for the quantity of computers. So does Online Test Engine. You can use Online Test Engine in any device.
Over 60261+ Satisfied Customers
