NEW QUESTION # 13
Which of the following processes lead to an entry in the MRP planing file?

  • A. Creation of sales order
  • B. Change of the storage bin
  • C. Creation of purchasing contract
  • D. Creation of dependent requirements
  • E. Change of the material's procurement type

Answer: A,D,E


NEW QUESTION # 14
What does the material type influence?

  • A. Which material master views can be maintained
  • B. Which document types are allowed
  • C. Which plant specific status is allowed
  • D. Whether the material is produced in-house, procured externally or bouth

Answer: A,D


NEW QUESTION # 15
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

  • A. Material requirements planning
  • B. Production order release
  • C. Backflushing
  • D. Kanban

Answer: A


NEW QUESTION # 16
What happens to this dependent requirement when you convert the planned order into a production order?

  • A. They are converted into a reservation.
  • B. They are converted into a planned order.
  • C. They are converted into a production order.
  • D. They are converted into a schedule line.

Answer: A


NEW QUESTION # 17
What does it mean for the production planner when MRP works with infinite capacities?

  • A. MRP creates capacity requirements only if the work center has sufficient capacity.
  • B. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
  • C. MRP creates capacity requirements without checking the capacity of a work center.
  • D. MRP assigns capacity requirements automatically after the last scheduled order on a work center.

Answer: C


NEW QUESTION # 18
Which materials have a negative quantity in a bill of materials or in a recipe?

  • A. By-products
  • B. Co-products
  • C. Continuous flow materials
  • D. Waste products
  • E. Bulk materials

Answer: A,B,C


NEW QUESTION # 19
Which SAP application can be used for forcasting in Supply Chain Planning?

  • A. Material Requirements Planning (MRP)
  • B. Integrated Business Planning (IBP)
  • C. Capacity Requirements Planning (CRP)
  • D. Supply Chain Management(SCM)

Answer: B,D


NEW QUESTION # 20
Which of the following questions do you have to answer before you start creating a BOM?

  • A. Is the material type allowed in the BOM?
  • B. Which Valid To information is necessary?
  • C. In which storage location is the BOM required?
  • D. What status does the BOM have?

Answer: A,B


NEW QUESTION # 21
Which information is required when you created a production master in SAP S/4HANA?

  • A. Selective screen for views
  • B. Industry sector
  • C. Base unit of measure
  • D. Product type

Answer: A,D


NEW QUESTION # 22
Which time elements are part of a routing operation?

  • A. Pick/pack time
  • B. Move time
  • C. Float before production
  • D. Wait time
  • E. Queue time

Answer: A,D,E


NEW QUESTION # 23
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?

  • A. SAP Ariba
  • B. SAP Concur
  • C. SAP Hybris
  • D. SAP SuccessFactors
  • E. SAP Fieldglass

Answer: A,B,E


NEW QUESTION # 24
You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.
What must you do?

  • A. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  • B. Add the agreement to the source list and mark it for MRP revalance.
  • C. Set the creation indicator for purchase requisitions on initial screen of MRP run
  • D. Add the agreement to the quota arrangement and mark it for MRP revalance.

Answer: A,B


NEW QUESTION # 25
How can you set up the supply source for the Kanban process in SAP S/4HANA?

  • A. Using purchasing costs for automated source prioritization
  • B. Using quotations for internal and external procurement
  • C. Using purchase orders for external procurement
  • D. Using run schedule quantities for in-house production
  • E. Using stock transfer reservations for stock transfer

Answer: C,D,E


NEW QUESTION # 26
You want to create a production order from a planned order. What methods could you use?

  • A. Order release
  • B. Collective conversion
  • C. Combined conversion
  • D. Partial conversion

Answer: B,D


NEW QUESTION # 27
How can SAP S/4HANA support a GMP-compliant production process?

  • A. Recipe approval
  • B. GMP-compliant flag
  • C. Digital signature
  • D. Batch record
  • E. Approved resources

Answer: A,C,D


NEW QUESTION # 28
Which master data object governs the relationship between supply source and demand source in the Kanban process?

  • A. Control cycle
  • B. Production supply area
  • C. Replenishment strategy
  • D. Rate routing

Answer: A


NEW QUESTION # 29
Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?

  • A. Archiving of documents for assembly scrap
  • B. Posting of production costs to the production cost collector
  • C. Material staging for nex order in sequence
  • D. Reduction of associated capacity requirements
  • E. Posting of goods receipt for the product

Answer: B,D,E


NEW QUESTION # 30
You are working with planning strategy 40 (Planning-with-final assembly) When does consuption of planned independent requirements take places?

  • A. When you deliver a sales order
  • B. When you create a sales order
  • C. When you create a planned order
  • D. When the MRP result are saved

Answer: B


NEW QUESTION # 31
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)

  • A. Use heuristic.
  • B. Use a resource group.
  • C. Use a propagation range.
  • D. Use a planning group.

Answer: A


NEW QUESTION # 32
......