Microsoft MB-335 certification exam is designed for professionals who want to become certified in Dynamics 365 Supply Chain Management Functional Consultant Expert. Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert certification exam covers a wide range of topics related to supply chain management, including inventory management, procurement, quality control, and production control. MB-335 exam is designed to test the candidate's knowledge and skills in these areas and to ensure that they are able to effectively implement and manage supply chain operations using Dynamics 365.

 

NEW QUESTION # 92
You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

Explanation:


NEW QUESTION # 93
A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin.
You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents pad of the solution.
NOTE: Each correct selection is worth one point.

  • A. Enter a value in the queue time after field for the painting operation.
  • B. Enter a value in the queue time before field for the assembly operation.
  • C. Enter a value in the transit time on the painting operation.
  • D. Make a resource group for each size and color and assign that group to the operation.
  • E. Build capabilities for each resource related to color.

Answer: A,B

Explanation:
Queue time is the time that a job waits at a work center before or after the job is processed1. You can use queue time to account for paint drying time before assembly operations can begin. You can specify queue time in minutes, hours, or days on the route operations that are attached to the production order2.
To set up the operation to encompass queue times, you should do the following:
Enter a value in the queue time after field for the painting operation. This value indicates how long the painted bicycle frames must wait at the painting work center before they can be moved to the next operation2. For example, if the paint drying time is 24 hours, you can enter 24 in the queue time after field and select Hours as the unit.
Enter a value in the queue time before field for the assembly operation. This value indicates how long the painted bicycle frames must wait at the assembly work center before they can be processed2. For example, if there is a delay between the arrival of the frames and the start of the assembly, you can enter a value that reflects this delay in the queue time before field and select the appropriate unit.
The other options are not correct, because they do not involve queue times. Building capabilities for each resource related to color would allow you to assign resources based on their color proficiency, but it would not account for paint drying time. Entering a value in the transit time on the painting operation would indicate how long it takes to move the painted bicycle frames from one work center to another, but it would not include the waiting time before or after the movement. Making a resource group for each size and color and assigning that group to the operation would allow you to group resources that have similar characteristics and can be used interchangeably in production, but it would not affect the queue times.
1: Queue times 2: Set up operations scheduling


NEW QUESTION # 94
A company produces custom-made bicycles that offer many different configurations.
Your standard bicycle, B-0001, is made with many common components such as a frame and wheels. Customers can choose between two frames: F-0001 or F-0009. Wheel W-0001 is only compatible with frame F-0001.
You create the following configuration groups: Frames, Wheels
You need to ensure that users can only select valid combinations of frames and wheels.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

1 - Assign the Frames and Wheels configuration..
2 - Create a new Bill of materials version..
3 - Add the Frames and Wheels configuration groups to the configuration route
4 - Configure the two bicycle configurations
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/pim/dimension-based-product-configuration


NEW QUESTION # 95
A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
* LegalEntityA: Plant 1.2, and 3
* LegalEntityB: Plant4and 5
* LegalEntityC: Plant 6. 7, and 8
The following plants must be planned together:
* Plant 1. Plant 3. and Plant 4
* Plant 2. Plant 6. and Plant 8
* Plant 5 and Plant 7
You need to configure master planning for the facilities.
Which configuration mechanism should you use?

  • A. Intercompany planning groups
  • B. Coverage groups
  • C. Production groups
  • D. Item model groups

Answer: A

Explanation:
The configuration mechanism that you should use is Intercompany planning groups. Here is the explanation:
* Intercompany planning groups are groups of companies that are planned together in master planning. Intercompany planning groups allow you to include planned downstream demand from other companies in your master plan, and also to peg across companies by using multilevel pegging1. You can use intercompany planning groupsto plan for intercompany sales and purchases, and to optimize the production capacity across companies1.
* In this scenario, you need to configure master planning for the facilities that must be planned together.
To do this, you should create intercompany planning groups that include the relevant plants from different legal entities. For example, you can create an intercompany planning group that includes Plant
1, Plant 3, and Plant 4 from LegalEntityA and LegalEntityB. You can also specify the schedulingsequence for the companies in the intercompany planning group, which determines the order in which master planning is run for each company1.
* The other options are not correct, because they do not involve intercompany planning. Production groups are groups of production orders that share the same parameters, such as ledger accounts and posting profiles2. Item model groups are groups of items that share the same inventory policies, such as reservation, tracking, and costing3. Coverage groups are groups of items that share the same coverage settings, such as coverage code, period, and time fence.
1: Intercompany planning 2: Production groups 3: Item model groups : [Coverage groups]


NEW QUESTION # 96
A company uses Discrete manufacturing concepts to produce cables. The company's production scheduler uses internal documents to track issues on in-process production orders.
The production scheduler must group all in-process production orders according to issues. The scheduler must be able to easily determine issues with production orders.
You need to implement a method to easily identify production orders with issues.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

Explanation:


NEW QUESTION # 97
A candy manufacturer uses Dynamics 365 Supply Chain Management.
A master planning run needs to prioritize the production jobs for fruit snacks by flavor and color every 16 days.
You need to configure the appropriate parameters in the coverage group.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

Explanation:


NEW QUESTION # 98
You need to address the ignition switch issue.
Which three actions should you perform? Each answer presents part of the solution.
NOTE: Each correct selection is worth one point.

  • A. Copy link and products.
  • B. Set product readiness to manual,
  • C. Define business impact.
  • D. Change product lifecycle state.
  • E. Set product readiness to automatic.

Answer: B,C,D


NEW QUESTION # 99
An automobile manufacturer leases cars to companies for use as company cars.
A car leased to a company breaks down and requires repairs.
You must open a maintenance request and replace the car with an equivalent model until the original car is repaired and returned to the company. When the manufacture' receives and inspects the car, the replacement car can be released to the company.
You need to select the maintenance request components to use.
Which components should you use? To answer, drag the appropriate components to the correct assets. Each component may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
Note: Each correct selection is worth one point.

Answer:

Explanation:

Explanation
To select the maintenance request components to use, you should use the following:
The leased car that must be repaired: You should use the component. An inbound asset is an asset that is received from a customer or vendor for maintenance or repair1. You can use the Inbound assets page to create and manage inbound assets in Asset Management2. You can also create a maintenance request for an inbound asset and link it to a work order3.
The replacement car for the leased car: You should use the Outbound asset component. An outbound asset is an asset that is sent to a customer or vendor as a temporary replacement for an asset that is being maintained or repaired1. You can use the Outbound assets page to create and manage outbound assets in Asset Management. You can also link an outbound asset to an inbound asset or a work order.
1: Inbound and outbound assets 2: Inbound assets 3: Create a maintenance request for an inbound asset :
[Outbound assets]


NEW QUESTION # 100
You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent.
Subproduction orders for the subcomponent must be created when estimating production orders.
You need to configure the BOM line to generate sub production orders.
Which BOM line type should you use?

  • A. Pegged supply
  • B. Item
  • C. Phantom
  • D. Vendor

Answer: A

Explanation:
* The BOM line type determines how the line is handled during master planning and batch order production1. The Item line type indicates that the item is amaterial or service that is directly consumed, and that doesn't require further explosion or pegged supply1. When you estimate a production order for an item that has a BOM line with the Item line type, a subproduction order is created for the item2.
* The other options are not correct, because they do not generate subproduction orders. The Vendor line type indicates that the item is purchased from a vendor and not produced internally1. The Phantom line type indicates that the item is an intermediate product that is used to simplify the design process and group complex products into engineering modules1. The Pegged supply line type indicates that the item is supplied by another production order or transfer order, and that the supply must be reserved before it can be consumed1.


NEW QUESTION # 101
You need to determine the batch values on the combined mix batches for OperatorA.
Which values should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Answer:

Explanation:

Explanation:


NEW QUESTION # 102
A company uses multiple Dynamics 365 applications to track and repair equipment.
The company wants to improve its repair order process. Repair technicians frequently encounter unexpected issues daily. The technicians must be empowered to address the issues and create new work orders by doing the following:
* Provide step-by-step, just-in-time training for work order completion in the field by using videos and text.
* Document work order creation in a single, printable document.
* Report on the use of hands-on training.
You need to implement a solution forth requirements.
Which solution should you implement for each requirement? To answer, drag the appropriate solutions to the correct requirements. Each solution may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

Answer:

Explanation:

Explanation:
To implement a solution for the requirements, you should use the following solutions:
* Just-in-time training: You should use Dynamics 365 Guides. This solution allows you to create interactive, step-by-step learning experiences for repair technicians in the field. You can use videos, images, and text to provide instructions and tips for work order completion. You can also use mixed reality tools to overlay holograms on physical objects and guide technicians through complex tasks.
* Work order creation document: You should use Dynamics 365 Supply Chain Management. This solution allows you to create and manage work orders for equipment maintenance and repair. You can use the Work order page to enter the details of the work order, such as the customer, the equipment, the service tasks, the materials, and the costs. You can also print a work order report that summarizes the information in a single document.
* Training reporting: You should use Dynamics 365 Guides. This solution allows you to track and analyze the usage and effectiveness of your guides. You can use Power BI dashboards to view metrics such as completion rates, duration, errors, and feedback for each guide and step. You can also filter the data by date, location, operator, or device.
[What is Dynamics 365 Guides?] : [Work orders overview] : [Print a work order report] : [Analyze guide effectiveness]


NEW QUESTION # 103
You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

1 - Create a product for all the bicycles
2 - Release the product to the two legal entities
3 - Create the BOM
4 - Define the configuration routes and rules
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/pim/dimension-based-product-configuration


NEW QUESTION # 104
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
* Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01.
* Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell.
* Create a production flow process activity using the painting work cell and the service item as the picking activity.
* Create a service term on the activity to tie the purchase agreement to the activity.
Does the solution meet the goal?

  • A. Yes
  • B. No

Answer: A

Explanation:
The solution meets the goal. Here is the explanation:
* To create a subcontracting activity for the painting service, you should use the following steps1:
* Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01. This step is correct, because you need to create a purchase agreement that defines the terms and conditions for purchasing the subcontracting service from the vendor1. You also need to add a purchase agreement line for SP-01 and specify the quantity and price of the service.
* Create a vendor resource and a work cell for outsourced painting, then add the resource to the
* work cell. This step is correct, because you need to create a resource that is assigned to the vendor account and add it to a resource group that represents the subcontracting work cell1. This way, you can assign the subcontracting activity to the vendor resource.
* Create a production flow process activity using the painting work cell and the service item as the picking activity. This step is correct, because you need to create a process activity that represents the subcontracting service in the production flow1. You also need to specify the painting workcell as the resource group and SP-01 as the product of the process activity. You also need to select the Generate license plate option on the mobile device menu item that is used for reporting as finished1.
* Create a service term on the activity to tie the purchase agreement to the activity. This step is correct, because you need to create a service term that links the purchase agreement line to the production flow process activity1. A service term defines how a service item is consumed in production and how it is invoiced by the vendor.
1: Activity-based subcontracting


NEW QUESTION # 105
A company uses multiple Dynamics 365 applications to track and repair equipment.
The company wants to improve its repair order process. Repair technicians frequently encounter unexpected issues daily. The technicians must be empowered to address the issues and create new work orders by doing the following:
* Provide step-by-step, just-in-time training for work order completion in the field by using videos and text.
* Document work order creation in a single, printable document.
* Report on the use of hands-on training.
You need to implement a solution forth requirements.
Which solution should you implement for each requirement? To answer, drag the appropriate solutions to the correct requirements. Each solution may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

Answer:

Explanation:

Explanation:
To implement a solution for the requirements, you should use the following solutions:
* Just-in-time training: You should use Dynamics 365 Guides. This solution allows you to create interactive, step-by-step learning experiences for repair technicians in the field. You can use videos, images, and text to provide instructions and tips for work order completion. You can also use mixed reality tools to overlay holograms on physical objects and guide technicians through complex tasks.
* Work order creation document: You should use Dynamics 365 Supply Chain Management. This solution allows you to create and manage work orders for equipment maintenance and repair. You can use the Work order page to enter the details of the work order, such as the customer, the equipment, the service tasks, the materials, and the costs. You can also print a work order report that summarizes the information in a single document.
* Training reporting: You should use Dynamics 365 Guides. This solution allows you to track and analyze the usage and effectiveness of your guides. You can use Power BI dashboards to view metrics such as completion rates, duration, errors, and feedback for each guide and step. You can also filter the data by date, location, operator, or device.
[What is Dynamics 365 Guides?] : [Work orders overview] : [Print a work order report] : [Analyze guide effectiveness]


NEW QUESTION # 106
You are using the manufacturing execution module in Dynamics 365 Supply Chain Management. License plate labels must be printed for products in the Report as finished step. You need to use the manufacturing execution functionality that meets this requirement. What should you use?

  • A. Job card terminal
  • B. Operations schedules
  • C. Report BOMs as finished
  • D. Load planning workbench

Answer: A

Explanation:
The manufacturing execution functionality that meets the requirement of printing license plate labels for products in the Report as finished step is License plates. Here is the explanation:
* License plates are unique identifiers that are assigned to containers, pallets, or individual items in inventory. License plates can be used to track and manage inventory throughout the warehouse processes, such as receiving, put away, picking, packing, and shipping1. License plates can also be used in production processes, such as reporting as finished and raw material picking2.
* To print license plate labels for products in the Report as finished step, you must enable the Generate license plate option on the mobile device menu item that is used for reporting as finished2. You must also set up a document routing layout and a document routing for license plate labels3. When you use the mobile device to report a production order as finished, the system will generate a license plate for the finished product and print a license plate label to the specified printer2. The license plate label can include information such as the item number, batch number, quantity, and barcode of the finished product3.
1: License plates 2: Enable license plate label printing 3: Document routing label layouts


NEW QUESTION # 107
You need to create the new summer limited edition bicycle in Dynamics 365 in preparation for taking orders.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

Explanation
Graphical user interface, text, application, email Description automatically generated

Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/pim/dimension-based-product-configuration


NEW QUESTION # 108
A company uses separate finished good item numbers for size variations of the same product.
The company wants to minimize the number of variously-sized items that are created.
You need to perform the setup to allow variants in size to the product master.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer:

Explanation:

Explanation: