NEW QUESTION # 29
What are the statuses supported by Quality Review request?
- A. New, Confirmed, Defect reported, Complete
- B. In process, Defect reported, Complete, Close
- C. New, Confirmed, In process, Complete
- D. New, In process, Complete, Close
Answer: D
NEW QUESTION # 30
Which buyer business requirements are addressed by SAP Ariba Supply Chain Collaboration? Note: There are
3 correct answers to this question.
- A. Spend visibility
- B. Contract management
- C. Subcontracting order
- D. Forecast visibility
- E. Consigned inventory
Answer: C,D,E
NEW QUESTION # 31
Which cXML message triggers upon the post goods issue for a component ship notice?
- A. Product Replenishment Message
- B. Receipt Request
- C. Component Consumption Request
- D. Product Activity Message
Answer: D
NEW QUESTION # 32
When will an invoice be generated in the Evaluated Receipt Settlement (ERS) process?
- A. After purchase order confirmation
- B. After purchase order
- C. After goods receipt
- D. After inbound delivery
Answer: C
NEW QUESTION # 33
What are the options available when suppliers create an order confirmation in Ariba Network? Note: There are
3 correct answers to this question
- A. Confirm Entire Order
- B. Reject Entire Order
- C. Deliver Line Item
- D. Update Line Items
- E. Approve Entire Order
Answer: A,B,D
NEW QUESTION # 34
Which of the following processes are included in Quality Collaboration? Note: There are 2 correct answers to this question.
- A. Quality of invoice
- B. Quality review
- C. Quality notification
- D. Cost of quality
Answer: B,C
NEW QUESTION # 35
What level can supplier managed inventory business transaction rules be set to? Note: There are 2 correct answers to this question.
- A. Country level
- B. Supplier group level
- C. Buyer group level
- D. Supplier level
Answer: B,D
NEW QUESTION # 36
Which of the following data can the supplier use to filter quality notifications on Ariba Network? Note: There are 2 correct answers to this question
- A. Serial number
- B. Customer
- C. Status
- D. Goods receipt
Answer: B,C
NEW QUESTION # 37
What options does a supplier have in the supplier managed inventory process? Note: There are 2 correct answers to this question.
- A. Replenishment Order
- B. Planned Shipment
- C. Manufacturing Visibility
- D. Forecast
Answer: A,B
NEW QUESTION # 38
Which of the following PO tolerances may trigger an order confirmation approval? Note: There are 3 correct answers to this question.
- A. Date
- B. Batch
- C. Supplier part ID
- D. Quantity
- E. Price
Answer: A,D,E
NEW QUESTION # 39
Where would a user maintain cross-reference configuration parameters during purchase order collaboration setup?
- A. Default Transaction Rules on Ariba Network (AN)
- B. Cloud Integration Gateway (CIG)
- C. SAP Project Reference Object (SPRO)
- D. Integrated Business Planning (IBP)
Answer: B
NEW QUESTION # 40
Which of the following documents are sent to the subcontractor as a copy document? Note: There are 2 correct answers to this question.
- A. Component Supplier Create Invoice
- B. Component Supplier Create Ship Notice
- C. Buyer Create Component Consumption
- D. Buyer Create PO Sent to Component Supplier
Answer: B,D
NEW QUESTION # 41
When does the buyer update the status of the Quality Notification to "Complete?
- A. When the Inspection Lot is accepted
- B. When the Quality Notification is closed
- C. When the Advance Ship Notice is delivered
- D. When the Quality Notification is updated with a root cause
Answer: D
NEW QUESTION # 42
Where in Ariba Network can a Supplier commit to a Forecast? Note: There are 2 correct answers to this question.
- A. Extended Collaboration Tab
- B. Planning Collaboration Tab
- C. Reports Tab
- D. Forecast Tab
Answer: B,D
NEW QUESTION # 43
What is the cXML message type for consignment movement?
- A. Ship Notice Request
- B. Receipt Request
- C. Product Activity Message
- D. ConsignMoveRequest
Answer: B
NEW QUESTION # 44
Which of the following are available forecast alerts in Supply Chain Monitor? Note: There are 3 correct answers to this question.
- A. Commit Shortages
- B. Commit Overages
- C. Missing Commits
- D. Approved Commits
- E. Decommits
Answer: A,C,E
NEW QUESTION # 45
When can a supplier create an Advanced Ship Notice in the Supplier Managed Inventory process using planned shipment?
- A. After the goods receipt has been generated or updated
- B. After the order confirmation has been sent to Ariba Network
- C. After the schedule line has been sent to Ariba Network
- D. After manufacturing visibility has been sent to Ariba Network
Answer: C
NEW QUESTION # 46
......
Updated Exam C-ARSCC-2308 Dumps with New Questions: https://www.actual4cert.com/C-ARSCC-2308-real-questions.html
Today Updated C-ARSCC-2308 Exam Dumps Actual Questions: https://drive.google.com/open?id=1XdCGjO3ZauIRbP1nCpE12Y9sBqlHqp-M